Maybellin: Setting tasks.
Morgan: Documenting tasks. (Details documentation on dotProject.)
Robert: Supervising and keeping tasks up to date.

Detailed Schedule:

Sprint 1: Documents & Prototype Assigned: January 30th Due: Febuary 17th

Sprint 2: Finalize TDD & Implmentation Assigned: Febuary 18th Due: Febuary 27th

Sprint 3: Implementation & Alpha Release Assigned: March 11th Due: March 25th

Sprint 4: Implementation Assigned: March 27th Due: April 15th

Sprint 5: Implementation & Beta Release Assigned: April 17th Due: April 29th

Sprint 6: Cleanup & Polish Assigned: April 30th Due: May 6th

Budget:
Student budget. $0.00. Just Time.

Risk Analysis:
Time management.

Localization Plan:
DotProject will be used to track milestones for the project.

Test Plan:
Will test at each stage of development, as well as multiple testings before prototypes are due.