Management

Team:

Detailed Schedule

Assignment Name

Date Assigned

Due Date

Sprint 1: Documents & Prototype

January 30th

Febuary 17th

Sprint 2: Finalize TDD & Implmentation

Febuary 18th

Febuary 27th

Sprint 3: Implementation & Alpha Release

March 11th

March 25th

Sprint 4: Implementation

March 27th

April 15th

Sprint 5: Implementation & Beta Release

April 17th

April 29th

Sprint 6: Cleanup & Polish

April 30th

May 6th

 

There will be more content added to the dotProject that will contain breakdowns of all components for each Sprint.

Budget

Less than $200, since no book and we lack an artistic talent some assets will be acquired online.

Risk Analysis

There is always the realization of time constraints, feature creep, and goals too high for current skill level.

Localization Plan

The game will only be produced in English

Test Plan

Every sprint a working deliverable will be available for testing. Each individual component will be tested by that programmer.